The works will include two toilets, rubbish chute, pipe (which we have decided not to do), grille and lifts (which we don't need as we are on lift-landing floor).
The schedule has just been sent to us, starting on the National Day week:
Day 1
- Protection to unit flooring & fixture. Hacking of spalling concrete (if any)
- Dismantle any obstruction, fixtures & fittings in common and MBR toilet.
- Hacking to common toilet and MBR toilet.
- Grinding of ceiling paint and wall paint to common toilet & MBR toilet (if any).
- Installation of temporary wc/bathroom to unit at the end of day.
Day 2
- Repair of spalling concrete to unit (patching).
- Replace sanitary pipr to kitchen, common toilet & MBR toilet.
- Grout infill to sanitary pipe opening.
Day 3
- Repair of spalling concrete to unit if any (skimming). Upgrade of electrical sub-main.
- Provide wall peg for bedding to common toilet and MBR toilet and MBR toilet wall.
- Replace refuse chute hopper.
- Form chamfering to wall & pipe surrounding at kit floor trap area, common toilet and MBR toilet.
- Apply non-shrink grout to kit floor trap area, common toilet & MBR toilet to level the floor.
- Skimming to common toilet and MBR toilet ceiling.
Day 4
- Apply 2 coats of waterproofing membrane to kitchen floor trap area, common toilet floor & MBR toilet floor.
- Apply non-shrink grout to kitchen pipe area, common toilet & MBR toilet.
Day 5
- Water test to kitchen floor trap area, common toilet abd MBR toilet floor.
- Floor screeding to common toilet and MBR toilet.
- Installation of new entrance gate.
Day 6
- Provide bedding to common toilet and MBR toilet and wall tiling.
- Replace louvered vent to common and MBR toilet.
Day 7
- Wall tiling to common toilet and MBR toilet.
Day 8
- Floor tiling to common toilet and MBR toilet.
- Reinstatement works to kitchen pipe surrounding.
Day 9
- Installation of sanitary fittings & grab bar to common toilet and MBR toilet.
- Installation of PVC bi-fold door to common toilet and MBR toilet.
- Reinstatement of electrical works & other fixtures to common & MBR toilet.
Day 10
- 2nd water test to common toilet and MBR toilet.
- Inspection to unit and defects rectification works.
- Painting, touch up and reinstatement works to common and MBR toilets.
- Cleaning up of unit. Handing over of unit to resident.
----------------------------PHEW--------------------------------------
In any case, MBR should be Master Bed Room. :)
Geez, now we are planning how to schedule ourselves to go 'jagar' during those 10 days.